Canistota FTTH 2021

Fiber to the Home 2021 
Canistota

Our fiber network will be expanded throughout the Canistota exchange including the town and rural areas. 

Schedule Appointment Button.png Short Intro Video.png

Project Updates

April 22, 2021

  • Engbarth Directional Drilling and their subcontractors will continue to work in the north west corner of town, burying mainline duct (pipe for mainline cable) and drop duct (pipe to customer premises). They will move next to the south part of town.
  • Travis Electric is scheduling installation of clamshells on homes and businesses in the town of Canistota. If you live in town and have not received a call from them, please call 1-855-888-7777 and ask for the engineering department.
  • Travis Electric will move to the rural part of the exchange when they have completed work in town.

April 16, 2021

  • Construction work has been concentrated in the northwest part of Canistota due to the wet conditions in the other parts of town.
  • Travis Electric is scheduling installation of clamshells on homes and businesses in the town of Canistota. If you live in town and have not received a call from them, please call 1-855-888-7777 and ask for the engineering department.
  • Travis Electric will move to the rural part of the exchange when they have completed work in town.

 April 8, 2021

  • Engbarth Directional Drilling will finish burying mainline orange duct in the area shown in blue on the map (Construction Area 1), then move their equipment to the area shown in purple (Construction Area 2).
  • Travis Electric is scheduling installation of clamshells on homes and businesses in the town of Canistota. If you live in town and have not received a call from them, please call 1-855-888-7777 and ask for the engineering department,
  • Travis Electric will move to the rural part of the exchange when they have completed work in town.

Canistota Construction Area 4-8-21.pdf

Canistota Map 4-8-21.PNG


 April 1, 2021

  • Construction is underway in the town of Canistota. Engbarth Directional Drilling will be starting work along Railway Avenue from Oak Street to Main Street, then will move east along Main Street to East Street. They will proceed north to Willow (261st ) Street.
  • EDD will also be working in the alley between Oak and Pine Streets from Railway Avenue to Third Street, then between Pine and Main Streets from Railway Avenue to Third Street. Drop crews will plow lines to premises behind the main line construction.
  • Travis Electric is scheduling installation of clamshells on homes and businesses in the town of Canistota. They will move to the rural part of the exchange when they have completed work in town.

Canistota Map 4-1-21 Construction Area.pdf

Canistota Map 4-1-21.PNG


 

FTTH Canistota lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in Canistota:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - Engbarth
Engineering Consultant - RVW Inc.

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.  


 

March 26, 2021
Project Update

  • Engbarth Directional Drilling is starting construction activity in town. Crews are marking underground utilities.
  • Travis Electric is scheduling installation of clamshells on homes and businesses in the town of Canistota.