Creighton FTTH 2021

Fiber to the Home 2021 
Creighton

Our fiber network will be expanded throughout the Creighton exchange. 

Short Intro Video.png

Project Updates

April 22, 2021

  • DME Electric has been completing Phase 1 wiring installations. They will be working in the area until they have the prewiring done in all customer homes.
  • Ripley’s will begin construction after completing the Milesville project. Work is expected to begin in a few weeks.

 April 16, 2021

  • DME Electric has begun Phase 1 wiring installations this week. They will be working in the area until they have the prewiring done in all customer homes.
  • Ripley’s will begin construction after completing the Milesville project. Work is expected to begin in early summer.

April 8, 2021

  • DME Electric will be calling Creighton customers to scheduling their Phase 1 wiring appointment. At this visit they will install the clamshell, or box, on the outside of the home, as well as doing some inside work.
  • Ripley’s will begin construction after completing the Milesville project. Work is expected to begin in early summer.

March 26, 2021

  • Ripley’s will begin construction after completing the Milesville project. Work is expected to begin in early summer.

 

FTTH Creighton lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in Creighton:

Wiring Contractor - DME Electric LLC
Construction Contractor - Ripley's Inc.
Engineering Consultant - RVW Inc.

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.