The first of a two-year project for the Kyle exchange, which includes the communities of Kyle and Allen and rural areas east of there. The remainder of the exchange is scheduled for 2022.  

Schedule Appointment Button.png Short Intro Video.png 

Project Updates

April 16, 2021

  • Travis Electric is scheduling installation of clamshells on homes and businesses in Kyle and Allen. They will move to the rural part of the exchange when they have completed work in town.
  • MasTec will begin construction on Monday in Kyle. They will plow the main lines and lines to customer homes (drops), then move to Allen, then to the rural areas.

April 8, 2021

  • Travis Electric is scheduling installation of clamshells on homes and businesses in Kyle and Allen. They will move to the rural part of the exchange when they have completed work in town.
  • MasTec will begin construction on Monday in Kyle. They will begin in this area:
      • North edge will be BIA #2 - Big Foot Trail
      • South edge will be Wakinya Ave
      • West side will be Mato Ave
      • East side will be BIA #4 – Allen Road

April 1, 2021

  • Travis Electric is scheduling installation of clamshells on homes and businesses in Kyle. They will move to the rural part of the exchange when they have completed work in town.
  • Customers will see activity in the area as contractors begin locating existing utility lines and moving in equipment. North Central Services will begin construction the week of April 12th.

March 18, 2021

  • Travis Electric started hanging clamshells this week. They will begin in the towns and then move to rural areas.
  • Customers will see activity in the area as contractors begin locating existing utility lines and moving in equipment.

 

FTTH KYLE lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in Kyle - Year 1:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - MasTec
Engineering Consultant - Heberly & Associates

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.  


March 26, 2021
Project Update

  • Travis Electric started hanging clamshells this week. They will begin in the towns and then move to rural areas.
  • Customers will see activity in the area as contractors begin locating existing utility lines and moving in equipment.