Sidney Park Rd & Sylvan Lake Rd - FTTH 2021

Fiber to the Home 2021 
Sidney Park Road & Sylvan Lake Road 

Our fiber network will be expanded to the members residing on Sidney Park Road and Sylvan Lake Road outside of Custer.

Schedule Appointment Button - Inactive.png  Short Intro Video.png

*Online appointment scheduling is currently unavailable.

Project Updates

July 22, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable along Hazelrodt Cutoff.
  • Travis Electric has been working in the area, installing clamshells on customer homes.

Sylvan Lake Road

  • North Central Services is burying cable in the Willow Creek Road area.
  • Travis Electric has been installing clamshells on customer premises.

 July 15, 2021

Sidney Park Road

  • May Construction has been working on another project. They plan to return to the Sidney Park area to resume construction work next week.
  • Travis Electric has been in the area, installing clamshells on customer homes.

Sylvan Lake Road

  • North Central Services is working along Willow Creek and Elk Valley Roads.
  • Travis Electric has been installing clamshells on customers premises.

July 8, 2021

Sidney Park Road

  • Customers who are included in the project should have received a letter from Golden West notifying them of the construction.
  • May Construction is plowing cables and installing drops in the Sidney Park Road area. They have moved to different locations on the project as landowner permissions are obtained.
  • Travis Electric has been calling customers to schedule installation of a box, or clamshell, on the outside of their home.

Sylvan Lake Road

  • Customers who are included in the project should have received a letter from Golden West notifying them of the construction.
  • North Central Services is plowing cable in the Sylvan Lake Road area.
  • Travis Electric has been calling customers to schedule installation of a box, or clamshell, on the outside of their home.

Sidney Park Area Boundary.PNG

Sylvan_Lake_Area_Boundary.png

FTTH Construction Overview

 Golden West Contractors for Sidney Park Road Project:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - May Construction
Engineering Consultant - Heberly & Associates

Golden West Contractors for Sylvan Lake Road Project:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - North Central Services
Engineering Consultant - Heberly & Associates

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.