West of Edgemont FTTH 2021

Fiber to the Home 2021 
West of Edgemont

Our network of fiber will be expanded to the rural area west of Edgemont including Dewey, Burdock and west to Mule Creek Junction. 

Short Intro Video.png

Project Updates

October 14, 2021

  • Due to the wet weather, work on construction was suspended on Tuesday afternoon.
  • Next week North Central Services will finish plowing fiber on Flat Top Road, then move back to Wyoming.
  • NCS has been scheduling Phase 1 wiring installations to prepare homes to get connected to fiber.

October 7, 2021

  • North Central Services is plowing fiber north of Edgemont on Dewey Road and Burdock Loop.
  • NCS has been scheduling Phase 1 wiring installations to prepare homes to get connected to fiber.

September 30, 2021

  • North Central Services is working on Highway 18 near the Cheyenne River, then they will move northwest of Edgemont.
  • NCS has been scheduling Phase 1 wiring installations to prepare homes to get connected to fiber.

September 23, 2021

  • North Central Services is working in Wyoming on Highway 85. Their crew will have time off over the weekend and return next week to work north of Edgemont.
  • NCS has been calling customers to schedule Phase 1 wiring installations to prepare homes to get connected to fiber.

September 16, 2021

  • North Central Services is burying fiber along Coffee Flats Road. Next week they expect to move to Highway 85 in Wyoming.
  • NCS will be calling customers to schedule a time to hang a box, or clamshell, on their house.

September 9, 2021

  • North Central Services is burying cable along US Highway 18 in Wyoming, heading east.
  • NCS will be calling customers to schedule a time to hang a box, or clamshell, on their house.

August 27, 2021

  • North Central Services is burying cable along US Highway 18 in Wyoming.
  • NCS will be calling customers to schedule a time to hang a box, or clamshell, on their house.

August 19, 2021

  • North Central Services is burying cable along River Road. They will move north by the end of the week.
  • NCS will be calling customers to schedule a time to hang a box, or clamshell, on their house.

August 12, 2021

  • North Central Services is boring under approaches along River Road. They will begin plowing cable on Monday.
  • NCS will be calling customers to schedule a time to hang a box, or clamshell, on their house.

August 5, 2021

  • North Central Services is proceeding with boring under approaches along US Highway 18.
  • NCS will be moving in materials in preparation for plowing to begin soon.

July 29, 2021

  • North Central Services has started work on the West Edgemont project. They will be have a boring rig burying pipe under approaches along US Highway 18, heading west.

 July 22, 2021

  • Construction will begin next Monday, when North Central Services starts work with their boring rig, heading west on Highway 18. Boring involves drilling underground to go underneath roads, driveways, flowing water, or other areas. A pipe is buried at the time of boring, so that later, the fiber optic cable can be pulled through the pipe.