Custer

Fiber to the Home Project

PROJECT UPDATE

Our fiber network will be expanded to the members residing on Sidney Park Road and Sylvan Lake Road outside of Custer.

April 14, 2022

Sidney Park Road

  • Travis Electric has completed connecting customers to fiber in this project area.

Sylvan Lake Road

  • Travis Electric has completed connecting customers to fiber in this project area.

April 7, 2022

Sidney Park Road

  • Travis Electric will be complete fiber upgrade installations in the project area this week.

Sylvan Lake Road

  •  Travis Electric will be complete fiber upgrade installations in the project area this week.

March 31, 2022

Sidney Park Road

  • Travis Electric will be in the area completing Phase 2 cut over installations next week.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department. 

Sylvan Lake Road

  • Travis Electric will be in the area completing Phase 2 cut over installations next week.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

March 24, 2022

Sidney Park Road

  • Travis Electric is nearly finished upgrading customers to fiber. They will return later this spring to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is nearly finished upgrading customers to fiber. They will return later this spring to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

March 17, 2022

Sidney Park Road

  • Travis Electric is nearly finished upgrading customers to fiber. They will return later this month to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is nearly finished upgrading customers to fiber. They will return later this month to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

March 10, 2022

Sidney Park Road

  • Travis Electric is nearly finished upgrading customers to fiber. They have been working in the area for the past week. They will return later this month to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is nearly finished upgrading customers to fiber. They have been working in the area for the past week. They will return later this month to finish the remaining installs.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

March 3, 2022

Sidney Park Road

  • Travis Electric will be doing wiring work and fiber upgrades in the coming week.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric will be doing wiring work and fiber upgrades in the coming week.
  • If you are a customer in this area who had fiber buried to your home and have not yet scheduled an installation, please call 1-855-888-7777 and ask for the engineering department.

February 24, 2022

Sidney Park Road

  • Travis Electric is in the area this week completing Phase 2 installations to connect customers to fiber.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is in the area this week completing Phase 2 installations to connect customers to fiber.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

February 17, 2022

Sidney Park Road

  • On Monday, Travis Electric will be returning to the Custer area to continue upgrading customers to fiber.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • On Monday, Travis Electric will be returning to the Custer area to continue upgrading customers to fiber.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

 February 10, 2022

Sidney Park Road

  • Travis Electric will be returning to the Custer area to continue upgrading customers to fiber on February 21st.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric will be returning to the Custer area to continue upgrading customers to fiber on February 21st.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

February 3, 2022

Sidney Park Road

  • Travis Electric is working on another project. They will return to the Custer area later this month.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is working on another project. They will return to the Custer area later this month.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

January 28, 2022

Sidney Park Road

  • Please notify Travis Electric or Golden West as soon as possible if you have an appointment scheduled and need to postpone due to illness.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Please notify Travis Electric or Golden West as soon as possible if you have an appointment scheduled and need to postpone due to illness.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department. 

January 13, 2022   

Sidney Park Road 

  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

January 6, 2022

Sidney Park Road

  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.

Sylvan Lake Road

  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.
  • If you are a customer in this area and have a question about scheduling or changing an appointment, please call 1-855-888-7777 and ask for the engineering department.


 

December 23, 2021

Sidney Park Road

  • May Construction has finished construction to areas that had existing Golden West service. Golden West is working on connecting customers who requested service after the project began. If you have questions, please call 1-855-888-7777 and ask for the engineering department.
  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.

Sylvan Lake Road

  • Technicians have finished testing the new fiber.
  • Starting in January, Travis Electric will be scheduling installation appointments to connect customers to the new fiber network.


December 17, 2021

Sidney Park Road

  • May Construction has finished construction to areas that had existing Golden West service. Next they will plow lines to customers who signed up for service after construction began.
  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks

Slyvan Lake Road

  • Technicians are working on splicing and testing fibers.
  • Starting in January, Travis Electric will be scheduling installation appointments to connect customers to the new fiber network.

December 10, 2021

Sidney Park Road

  • May Construction has nearly finished construction to areas that had existing Golden West service. Next they will plow lines to customers who signed up for service after construction began.
  • Travis Electric is scheduling Phase 2 installations to connect customers to fiber. This work will continue for the next several weeks.

Slyvan Lake Road

  • NCS has one area left to plow on Bonanza Road.
  • Once construction is complete, fiber splicers will finish splicing and testing the last of the new fibers.
  • Splicing and testing will be followed by wiring work in the Custer Golden West central office.
  • In a few weeks, Travis Electric will begin scheduling installation appointments.

December 3, 2021

Sidney Park Road

  • May Construction has been working on Deer Meadow Road and Flynn Creek Road.
  • May Construction has nearly finished construction to areas that had existing Golden West service. Next they will plow lines to customers who signed up for service after construction began.
  • Travis Electric began Phase 2 wiring work to upgrade customers to fiber this week. This work will continue for the next several weeks.


November 23, 2021

Sidney Park Road

  • May Construction has been working on Deer Meadow Road and Flynn Creek Road.
  • Travis Electric will begin scheduling Phase 2 wiring appointments for the first group of customers, with work planned to start on November 29th.

Sylvan Lake Road

  • May Construction has been working on Deer Meadow Road and Flynn Creek Road.
  • Travis Electric will begin scheduling Phase 2 wiring appointments for the first group of customers, with work planned to start on November 29th.
  • NCS has one area left to plow on Bonanza Road.
  • Once construction is complete, fiber splicers will finish splicing and testing the last of the new fibers.
  • Splicing and testing will be followed by wiring work in the Custer Golden West central office.
  • In a few weeks, Travis Electric will begin scheduling installation appointments.

November 10, 2021

Sidney Park Road

  • May Construction is working on Flynn Creek and Glenn Erin Roads.
  • Golden West is splicing and testing fibers on West View Road, then will move to Flynn Creek Road.
  • Travis Electric will begin scheduling Phase 2 wiring appointments for the first group of customers, with work planned to start on November 29th.

Sylvan Lake Road

  • Splicers are pulling fibers from the main line to customer homes, splicing as they go.


October 28, 2021

Sidney Park Road

  • May Construction is working on Flynn Creek and Glenn Erin Roads.
  • Golden West is splicing and testing fibers.
  • The first segment of the project is ready to be converted from copper to fiber. Customers will receive letters to notify them that Travis Electric will be calling them to schedule an installation. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • The splicing crew is working out of the area, but will return next week to finish splicing and testing fibers.

October 21, 2021

Sidney Park Road

  • May Construction will be working on Flynn Creek Road when weather permits.
  • The first group of customers will soon be notified by letter that Travis Electric will be contacting them to schedule a Phase 2 installation to connect them to fiber. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • A crew is splicing fibers and will be working along the mainline and also on customer premises.

October 14, 2021

Sidney Park Road

  • Snow earlier this week put a stop to construction for a few days.
  • May Construction will be moving equipment to Flynn Creek and will resume work when weather permits.
  • In the next few weeks, the first group of customers will be notified by letter that Travis Electric will be contacting them to schedule a Phase 2 installation to connect them to fiber. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • After a pause due to the recent snow storm, contractors will continue burying lines to customer homes on the south end of Sylvan Lake Road.

October 7, 2021

Sidney Park Road

  • May Construction is burying fiber on West View Road. They will be working on Flynn Creek Road next.
  • In the next few weeks, the first group of customers will be notified by letter that Travis Electric will be contacting them to schedule a Phase 2 installation to connect them to fiber. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • Contractors are burying lines to customer homes Sylvan Lake Road north of Willow Creek Road.

September 30, 2021

Sidney Park Road

  • May Construction is burying fiber along Pony Express Place, then will move to Westview Place.
  • In the next few weeks, the first group of customers will be notified by letter that Travis Electric will be contacting them to schedule a Phase 2 installation to connect them to fiber. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • Contractors are burying lines to customer homes on the south end of Sylvan Lake Road.

September 23, 2021

Sidney Park Road

  • May Construction has finished construction on Hazelrodt Cutoff. They are currently working on Pony Express Place.
  • In the next few weeks, the first group of customers will be notified by letter that Travis Electric will be contacting them to schedule a Phase 2 installation to connect them to fiber. This process will continue until all customers in the project area have been cut over to the new fiber network.

Sylvan Lake Road

  • Contractors are burying lines to customer homes in the Sylvan Lake area. They are currently working on Willow Creek Road, then will move to the south end of Sylvan Lake Road.

September 16, 2021

Sidney Park Road

  • May Construction is working on Pony Express. They will proceed along Westview Road, then move to Flynn Creek Road.

Sylvan Lake Road

  • Contractors are burying lines to customer homes in the Sylvan Lake area. They expect this work to continue through October.

September 9, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable on Deer Meadow Road near Zebroski Lane.

Sylvan Lake Road

  • North Central Services and their subcontractor will begin burying lines to customer homes on September 13th.

August 27, 2021

Sidney Park Road

  • The next construction update will be posted the week of September 6th. Have a safe and relaxing Labor Day holiday!
  • May Construction is burying fiber optic cable on Hazelrodt Cutoff, then will move to Deer Meadow Road.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

Sylvan Lake Road

  • The next construction update will be posted the week of September 6th. Have a safe and relaxing Labor Day holiday!
  • North Central Services has completed mainline construction. They are currently working on cleanup.
  • Construction on lines to customer homes will begin soon.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

August 19, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable on Hazelrodt Cutoff, going east.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

 Sylvan Lake Road

  • North Central Services is burying cable along Sylvan Lake Road.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

August 12, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable on Holiday Trail.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

Sylvan Lake Road

  • North Central Services will be working along Bonanza Road, then will move to Sylvan Lake Road.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

 August 5, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable along Hazelrodt Cutoff, headed toward Sidney Park Road (see map).
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

Sylvan Lake Road

  • North Central Services is sawing rock on Willow Creek Road. They have a mainline plow working on Quarry Road.
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

 July 29, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable along Hazelrodt Cutoff, headed toward Sidney Park Road (see map below).
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

Sylvan Lake Road

  • North Central Services is sawing rock on Quarry Road. They are plowing on Sylvan Lake Road (see map below).
  • Travis Electric has finished installing boxes, or clamshells, on customer premises.

Custer SLR and SPR Construction Area.pdf

Custer SLR and SPR Construction Area.png


July 22, 2021

Sidney Park Road

  • May Construction is burying fiber optic cable along Hazelrodt Cutoff.
  • Travis Electric has been working in the area, installing clamshells on customer homes.

Sylvan Lake Road

  • North Central Services is burying cable in the Willow Creek Road area.
  • Travis Electric has been installing clamshells on customer premises.

 July 15, 2021

Sidney Park Road

  • May Construction has been working on another project. They plan to return to the Sidney Park area to resume construction work next week.
  • Travis Electric has been in the area, installing clamshells on customer homes.

Sylvan Lake Road

  • North Central Services is working along Willow Creek and Elk Valley Roads.
  • Travis Electric has been installing clamshells on customers premises.

July 8, 2021

Sidney Park Road

  • Customers who are included in the project should have received a letter from Golden West notifying them of the construction.
  • May Construction is plowing cables and installing drops in the Sidney Park Road area. They have moved to different locations on the project as landowner permissions are obtained.
  • Travis Electric has been calling customers to schedule installation of a box, or clamshell, on the outside of their home.

Sylvan Lake Road

  • Customers who are included in the project should have received a letter from Golden West notifying them of the construction.
  • North Central Services is plowing cable in the Sylvan Lake Road area.
  • Travis Electric has been calling customers to schedule installation of a box, or clamshell, on the outside of their home.

Sidney Park Area Boundary.PNG

Sylvan_Lake_Area_Boundary.png

Golden West Contractors for Sidney Park Road Project:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - May Construction
Engineering Consultant - Heberly & Associates

Golden West Contractors for Sylvan Lake Road Project:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - North Central Services
Engineering Consultant - Heberly & Associates

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.