Milesville FTTH 2021

Fiber to the Home 2021 
Milesville

Our fiber network will be expanded throughout the Milesville exchange. 

Short Intro Video.png

Project Updates

April 22, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s is plowing south on Fitch Road, south of 204th Street.

April 16, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s has been plowing along King School Road and south of Fitch Road.

April 8, 2021

  • DME is nearly finished with Phase 1 wiring installations. If you live in the Milesville exchange and do not have a clamshell installed, please call 1-855-888-7777 and ask for the engineering department.
  • Ripley’s has been working north of Milesville on 202nd St, heading west.

 April 1, 2021

  • DME is scheduling Phase 1 installations. During this wiring appointment they will install the clamshell, or box, on the outside of the home, as well as doing some inside work.
  • Ripley’s has been moving equipment and materials to the area. They plan to begin work on April 6th.

March 26, 2021

  • DME has begun scheduling Phase 1 installations. During this wiring appointment they will install the clamshell, or box, on the outside of the home, as well as doing some inside work.
  • Ripleys will begin moving equipment and materials to the Milesville area. They plan to begin construction on April 5th.

FTTH Milesville lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in Milesville:

Wiring Contractor - DME Electric LLC
Construction Contractor - Ripley's Inc.
Engineering Consultant - RVW Inc.

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.