Milesville FTTH 2021

Fiber to the Home 2021 
Milesville

Our fiber network will be expanded throughout the Milesville exchange. 

Short Intro Video.png

Project Updates

July 29, 2021

  • DME Electric will finish connecting all customers in the project area to fiber this week.

July 1, 2021

  • Later this month DME will be calling Milesville customers to schedule appointments to complete Phase 2 wiring to cut over services from copper to fiber.

June 17, 2021

  • Customers in the Milesville project area should expect a letter notifying them that DME will begin scheduling Phase 2 cutovers soon. This installation will complete the work necessary to connect homes to the new fiber optic system.

 June 3, 2021

  • DME will begin Phase 2 wiring in a few weeks. They will be calling customers to schedule the upgrade to the new fiber optic system.
  • Ripley’s has completed burying cable in the Milesville area. Fiber splicers have completed splicing and testing fiber optic cables.
  • During the next stage of the project, Golden West will be working in the local central office to connect the fibers coming from each customer premise to the fiber network.

May 27, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s has completed burying cable in the Milesville area.
  • Fiber splicers have completed splicing and testing the new fiber optic cables.
  • During the next stage of the project, Golden West will be working in the local central office to connect the fibers coming from each customer premise to the fiber network.

May 21, 2021
  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project. After the fiber optic cables have been buried, spliced, and tested, they will return later in the summer to begin Phase 2 installations to connect customers to the new fiber.
  • Ripley’s has completed burying cable in the Milesville area. Fiber splicers are connecting lines coming from customer premises to the main line cables and testing fibers.

May 13, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s has completed burying cable in the Milesville area. Next week, fiber splicers will be working in the area, connecting lines coming from customer premises to the main line cables and testing fibers.

 May 6, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s is plowing cable on Quinn Road, north of Hardingrove Road. A second crew is on Tornado Ranch Road, south of Highway 34. Two crews are plowing lines to customer homes in this area.

April 29, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripleys is plowing cable on Highway 34 east of Quinn Road.

 April 22, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s is plowing south on Fitch Road, south of 204th Street.

April 16, 2021

  • DME has completed Phase 1 wiring installation for customers in the Milesville FTTH Project.
  • Ripley’s has been plowing along King School Road and south of Fitch Road.

April 8, 2021

  • DME is nearly finished with Phase 1 wiring installations. If you live in the Milesville exchange and do not have a clamshell installed, please call 1-855-888-7777 and ask for the engineering department.
  • Ripley’s has been working north of Milesville on 202nd St, heading west.

 April 1, 2021

  • DME is scheduling Phase 1 installations. During this wiring appointment they will install the clamshell, or box, on the outside of the home, as well as doing some inside work.
  • Ripley’s has been moving equipment and materials to the area. They plan to begin work on April 6th.

March 26, 2021

  • DME has begun scheduling Phase 1 installations. During this wiring appointment they will install the clamshell, or box, on the outside of the home, as well as doing some inside work.
  • Ripleys will begin moving equipment and materials to the Milesville area. They plan to begin construction on April 5th.

FTTH Milesville lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in Milesville:

Wiring Contractor - DME Electric LLC
Construction Contractor - Ripley's Inc.
Engineering Consultant - RVW Inc.

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.