Pine Ridge FTTH 2021

Fiber to the Home 2021 
Pine Ridge Exchange

Our fiber network will be expanded throughout the Pine Ridge exchange including the Porcupine and Wounded Knee areas.

Schedule Appointment Button.png Short Intro Video.png 

Project Updates

April 16, 2021

  • Travis Electric is installing clamshells on homes and businesses in Porcupine and Manderson. They will move to the rural part of the exchange when they have completed work in town.
  • North Central Service is working on Porcupine School Road and Pahin Sinte Street in Porcupine. See maps for Construction Areas 3 through 6.

Porcupine Contruction Area 3.jpg

Porcupine Contruction Area 4.jpg

Porcupine Contruction Area 5.jpg

Porcupine Contruction Area 6.jpg


 

April 8, 2021

  • Travis Electric is installing clamshells on homes and businesses in Porcupine and Manderson. They will move to the rural part of the exchange when they have completed work in town.
  • North Central Service started plowing mainline fiber on Porcupine School Rd. A crew will begin to bury lines, or drops, to customer premises in this area this week.
  • The maps show areas where construction will begin, with duct (orange pipe) being placed first.

Pine Ridge Rural Construction Area 1.pdf

PIne Ridge Area 1 4-8-2021.PNG

Pine Ridge Rural Construction Area 2.pdf

PIne Ridge Area 2 4-8-2021.PNG


 April 1, 2021

  • Travis Electric is scheduling installation of clamshells on homes and businesses in the Porcupine and Manderson. They will move to the rural part of the exchange when they have completed work in town.
  • North Central Service will begin construction next week. They plan to start in Porcupine.

 March 26, 2021

  • Travis Electric started hanging clamshells this week. They will begin in the towns and then move to rural areas.
  • North Central Service will begin construction on April 5th.

 

FTHH Pine Ridge Rural lo-cropped.jpg

FTTH Construction Overview

Golden West Contractors in rural Pine Ridge:

Wiring Contractor - Travis Electric, Inc.
Construction Contractor - North Central Service
Engineering Consultant - RVW Inc.

Please contact Golden West with any questions, concerns or comments by calling 1-855-888-7777 and asking for the Engineering Department or Email info@goldenwest.com.  


March 26, 2021
Project Update

  • Travis Electric started hanging clamshells this week. They will begin in the towns and then move to rural areas.
  • North Central Service will begin construction on April 5th.