Enter your address in the form below to verify your address is part of this project and that it should have a broadband internet connection from Golden West available by the end of 2024. If you see, "Good News" and complete the form provided to preorder service. Then Golden West will contact you to schedule the first appointment to bring the infrastructure to your home or business.
Enter your physical address to get started:
Project Details
The Caputa area running along U.S. Highway 44 east of Rapid City and to the south will be added to the Golden West fiber network in 2024.
Contractors:
Pre-Wiring & Installs – Golden West
Engineering Consultant – RVW, Inc.
Construction Contractor – MasTec North America
Customer Service – Golden West
Broadband internet access is coming
to the Caputa area!
Golden West's fiber-optic network connection will allow you to perform everyday activities online more easily for education, business, healthcare, entertainment, and more.
CHR Solutions, a contractor working for Golden West, began construction in the area in May. For your safety, every worker has a Golden West name badge. Those at eligible addresses who pre-order service should have a broadband connection by the end of 2024 or very early in 2025.
At that time the following speeds will be available – with no data limits and no contracts – as follows:
- up to 250 Mbps – $64.95/month
- up to 500 Mbps – $84.95/month
- up to 1 Gbps (1 Gig) – $104.95/month
Golden West also offers Wi-Fi plans to serve all of your many wireless devices.
- Ultimate Wi-Fi – $11.00/month. This plan offers exceptional security protection and access control, along with a router lease and Golden West Wi-Fi technical support.
- Managed Wi-Fi – $6.00/month. This plan includes a router lease and Golden West Wi-Fi technical support.
Don't miss this opportunity!
Sign up this summer while work is in progress to get free installation and avoid construction charges that may apply later. An advanced payment of $60.00 will be collected later before service is activated. For more details about the project, review this handout.
2024 PROJECT UPDATES
November 21, 2024
- MasTec has a plow burying mainline fiber between Radar Hill and Long View Roads.
- A second crew is plowing from Radar Hil Road south from the highway, moving toward Redemption Road.
- Splicers continue to work on connecting the new fibers.
- Construction crews will be off next week for the Thanksgiving holiday. Splicers will be on site Monday through Wednesday next week.
- Golden West is installing clamshells on homes for people who have signed up for service.
November 14, 2024
- MasTec has a plow burying mainline fiber north and west of Radar Hill Rd, working toward Anderson Road.
- A second crew is plowing driveways off Bradsky Road.
- Splicers continue to work on connecting the new fibers.
- Golden West is installing clamshells on homes for people who have signed up for service.
November 7, 2024
- MasTec has a plow crew working on E Highway 44 moving west from Airport Road.
- A second crew is plowing down Bradsky Road.
- Splicers are working on connecting the new fibers.
- Golden West is installing clamshells on homes for people who have signed up for service.
October 31, 2024
- MasTec will have one plow crew working on E Highway 44 near Airport Road.
- A second crew is plowing along Bradsky Road and Galloway Drive.
- Splicers are working on connecting the new fibers.
- Golden West is installing clamshells on homes for people who have signed up for service.
October 24, 2024
- MasTec will have one plow crew working on E Highway 44, moving west.
- A second crew is moving south on Bradsky Road from E Highway 44.
- Splicers are working on connecting the new fibers.
- Golden West is installing clamshells on homes for people who have signed up for service.
October 17, 2024
- MasTec will have one plow crew working on E Highway 44, heading southeast from Caputa.
- A second crew is working on Bradsky Road and E Highway 44, moving south.
- Splicers are working on connecting the new fibers.
- Golden West is installing clamshells on homes for people who have signed up for service.
October 10, 2024
- Crews returned to the project on Wednesday.
- MasTec has a crew plowing on Lamb Road.
- A second plow is working on Old Folsom Road.
- Golden West is installing clamshells on homes for people who have signed up for service.
October 3, 2024
- Crews were off this week. Construction will resume on October 9.
- Golden West is installing clamshells on homes for people who have signed up for service.
September 26, 2024
- Crews will be away for the next several days. Construction will resume on October 9.
- Golden West is installing clamshells on homes for people who have signed up for service.
September 19, 2024
- MasTec has one plow burying fiber north of Antelope Road on Old Folsom Road.
- The second main line plow is working on 154th Avenue.
- Three bore crews are working on the project. The first is on Old Folsom Road, the second is on Justice Lane, and the third is working in the Back Country Trail subdivision.
- Golden West is installing clamshells on homes for people who have signed up for service.
September 12, 2024
- MasTec has one plow burying fiber on Antelope Road and Old Folsom Road.
- The second main line plow is working on Long View Road.
- A bore crew is drilling and inserting vacant duct on Highway 44 near the airport.
- A drop crew is burying fiber to customer premises on Antelope Creek Road.
- Golden West is installing clamshells on homes for people who have signed up for service.
September 5, 2024
- MasTec has one plow burying fiber on Long View Road and Justice Lane.
- The second main line plow is working on Antelope Creek Road. A bore crew is also working in this area.
- A second bore crew is on Derby Lane, while the third bore machine is on Caputa Loop.
- A drop crew is burying fiber to customer premises on 154th Avenue.
- Golden West is installing clamshells on homes for people who have signed up for service.
August 29, 2024
- Most of the crews will be off on rotation over the Labor Day weekend, so construction activity will be limited between August 28 and September 4.
- Work will resume next Wednesday with one crew working three miles west of Dancing Wolf and the second crew near Justice Lane and Longview Road.
- Golden West is installing clamshells on homes for people who have signed up for service.
August 22, 2024
- MasTec is plowing mainline cable south of Dancing Wolf development on Antelope Creek Road.
- A bore crew is drilling and inserting pipe underground in the Dancing Wolf area.
- The second plow is on Long View Road, along with a bore crew.
- A third bore crew is working on Justice Lane.
- A crew is burying fiber to customer homes on Highway 44 and Antelope Creek Road.
- Most of the crews will be off on rotation over the Labor Day weekend, so construction activity will be limited between August 28 and September 4.
- Golden West is installing clamshells on homes for people who have signed up for service.
August 15, 2024
- MasTec has crews boring and plowing in several areas in the project.
- A bore crew is on 154th Avenue north of Caputa.
- Crews are also working in the Dancing Wolf subdivision area, working toward Antelope Creek Road.
- Golden West is installing clamshells on homes for people who have signed up for service.
August 1, 2024
- MasTec is plowing on Dawkins Road
- A bore crew is working north of town.
- A crew is plowing lines to customer homes east of Caputa.
- Golden West is installing clamshells on homes for people who have signed up for service.
July 25, 2024
- MasTec has two crews boring and inserting pipe in town.
- A plow crew is burying both main line fiber cable and drops, or lines to customer homes, on 158th Avenue headed north.
- Golden West is installing clamshells on homes for people who have signed up for service.
July 18, 2024
- MasTec has a bore crew and a crew plowing lines to customer homes working in the area.
- By next week they plan to have two mainline plows running.
- Golden West is installing clamshells on homes for people who have signed up for service.
July 11, 2024
- MasTec has a bore crew and a mainline plow crew working east of Caputa, heading west toward town.
- Crews are also boring under approaches and setting vaults.
- MasTec will be bringing in more equipment and people starting next week. They will start plowing mainline cable south of Caputa.
- Golden West is installing clamshells on homes for people who have signed up for service.
June 27,2024
- MasTec has a bore crew and a mainline plow crew working east of Caputa, heading west toward town.
- Golden West is installing clamshells on homes for people who have signed up for service.
June 20, 2024
- MasTec has a subcontractor boring on 150th off Highway 44.
- They will begin mainline plowing next week.
- Golden West is installing clamshells on homes for people who have signed up for service.
June 13, 2024
- MasTec has started construction with a bore rig drilling and inserting pipe under approaches and waterways.
- They will be moving equipment and materials in preparation for plowing to begin next week.
- Golden West is installing clamshells on homes for people who have signed up for service.
June 6, 2024
- Golden West is installing clamshells on homes for people who have signed up for service.
- Construction on the project will begin soon.
May 30, 2024
- Golden West is installing clamshells on homes for people who have signed up for service.
- Construction on the project will begin in June.
May 23, 2024
- Golden West is installing clamshells on homes for people who have signed up for service.
- Construction on the project will begin in June.
May 15, 2024
- Golden West is installing clamshells on homes for people who have signed up for service.