Hot Springs Southeast

The Hot Springs Southeast (rural) will be upgraded to fiber in 2025. This will complete the upgrade of the Hot Springs exchange. 

Contractors:
Wiring Contractor – Vantage Point
Engineering Consultant – Heberly & Associates
Construction Contractor – MasTec North America

Overview Video Update Contact Information

Hot Springs Phase 1 2024 FTTP.PNG

Project Updates:

June 26, 2025

  • MasTec has a directional drilling crew working on the west side of Cascade Road between Shep’s Canyon Rd and the road to the Nature Conservancy.
  • The mainline plow crew is plowing and pulling cable along Shep’s Canyon and Horseshoe Bend Roads as well as private drives off these roads.
  • Crews are burying lines to customer homes on Cascade, Pine Shadows, Jenny, Forest, and Himmelwright Roads.
  • The pre-rip crew is working along private drives and county roads along Cascade Road.
  • Construction crews will be away next week. They will return on July 7th.
  • If you have questions about the Fiber to the Home project, please call Golden West at 1-855-888-7777 and ask for the engineering department.

Hot Springs 2025 construction 6-25-25.png

 

June 19, 2025

  • Vantage Point is installing clamshells on customer premises.
  • MasTec has a directional drilling crew working on Cascade Road between Shep’s Canyon Rd and E Cascade Mountain Road.
  • The second bore crew is working up Horseshoe Bend Road, then will move to the west side of Cascade Road.
  • MasTec’s mainline plow crew is pulling cable along Shep’s Canyon Road and Horseshoe Bend Road between Cascade Road and Copper Canyon Road.
  • Crews are burying lines to customer homes on Cascade, Pinecone, Pine Shadows, Jenny and Forest Roads.
  • The pre-rip crew is working along private drives along Cascade Road.
  • If you have questions about the Fiber to the Home project, please call Golden West at 1-855-888-7777 and ask for the engineering department.

Hot Springs 2025 construction 6-19-25.png

 

June 12, 2025

  • Vantage Point is installing clamshells on customer premises.
  • MasTec has a directional drilling crew working on side roads between Shep’s Lodge and Shep’s Heights and along Cascade Road.
  • The second bore crew is working up Horseshoe Bend Road, then will move to the west side of Cascade Road.
  • MasTec’s mainline plow crew is pulling cable along Cascade Road between Shep’s Canyon Road and Horseshoe Bend Road. They will move next to the west side of Cascade Road.
  • Crews are burying lines to customer homes on Cascade, Pinecone, Pine Shadows, Jenny and Forest Roads.
  • MasTec is rock sawing on side roads and private drives.
  • If you have questions about the Fiber to the Home project, please call Golden West at 1-855-888-7777 and ask for the engineering department.

Hot Springs 2025 construction 6-12-25.png

 

May 29, 2025

  • Vantage Point is installing clamshells on customer premises.
  • MasTec has a bore crew working near Angostura reservoir in the Paradise Cove trailer park.
  • The second bore crew is working along SD Highway 71/Cascade Road, starting on the east side, then moving to the west side.
  • MasTec’s mainline plow crew is pulling cable along Shep’s Canyon Road between Morning Star Trail and Lake Hills Road, moving east.
  • Crews are burying lines to customer homes on Cascade Road, Lariat Circle, Cascade Springs Road, Black Hills Flyaway Road, Kitty Hawk Lane, Pinecone Road, Pine Shadows Road, and Forest Road.
  • MasTec is rock sawing along SD Highway 71/Cascade Road at the Nature Conservancy, moving south. A second rock saw is working along Shep’s Canyon Road, working east.
  • If you have questions about the Fiber to the Home project, please call Golden West at 1-855-888-7777 and ask for the engineering department.